A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?
A.
Prepare a WBS for immediate tasks in the plan to work package level for duration and cost estimates.
B.
Prepare a work breakdown structure (WBS) to include each deliverable with a target duration and cost estimate.
C.
Prepare a WBS to work package level to effectively manage duration and cost estimates.
D.
Prepare a WBS with task sequencing and detail the duration and cost estimates.