Which scenario is most desirable during the execution phase of a project?


A.

Apply and use quality controls to ensure expectations are met throughout the project


B.

Communicate quality failures to the sponsor for feedback


C.

Conduct all quality inspections at the end of the project


D.

Only correct quality issues found if it will keep you within the budget