Spring Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 37 Topic 7 Discussion

CAPM Exam Topic 7 Question 37 Discussion:
Question #: 37
Topic #: 7

The table represents the possible durations of a specific project task.

CAPM Question 37

Using the three-point estimating technique what is the expected number of days it should take to complete the task?


A.

2


B.

3


C.

4


D.

6


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.