Question #: 66
Topic #: 7

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?


A.

0.8


B.

0.89


C.

1.13


D.

1.25