A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?


A.

Allow team members to share project status reports.


B.

Perform qualitative risk analysis.


C.

Extend an iteration review invite to the new stakeholder.


D.

Engage with the new stakeholder.