Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam CAPM All Questions
Exam CAPM All Questions

View all questions & answers for the CAPM exam

PMI CAPM CAPM Question # 49 Topic 9 Discussion

CAPM Exam Topic 9 Question 49 Discussion:
Question #: 49
Topic #: 9

The following is a network diagram for a project.

CAPM Question 49

The total float for the project is how many days?


A.

5


B.

9


C.

12


D.

14


Get Premium CAPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.