PMI CAPM CAPM Question # 52 Topic 9 Discussion

CAPM Exam Topic 9 Question 52 Discussion:
Question #: 52
Topic #: 9

Progressively elaborating high-level information into detailed plans is performed by the:


A.

project management office


B.

portfolio manager


C.

program manager


D.

project manager