PMI Portfolio Management Professional PfMP Question # 6 Topic 1 Discussion

PfMP Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

You are managing a large portfolio and know that you will need to constantly show the progress and status of the portfolio in meeting. For this you have developed a robust roadmap using BI tools. The portfolio roadmap is used abundantly as an input to 7 processes. When it comes to managing portfolio value, how is the portfolio roadmap used?


A.

Delays in delivery of portfolio component results may adversely affect the value derived from the portfolio


B.

It is not used in managing the portfolio value


C.

Dependencies shown at the roadmap level have negative impacts on the value realized


D.

Dependencies shown at the roadmap level have positive impacts on the value realized