PMI Portfolio Management Professional PfMP Question # 106 Topic 11 Discussion

PfMP Exam Topic 11 Question 106 Discussion:
Question #: 106
Topic #: 11

You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the communication closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust Communication management plan. What is the result of developing this plan?


A.

Portfolio Process Assets updates, Portfolio Charter updates, Portfolio updates, Portfolio Management Plan updates, Enterprise Environmental Factors updates


B.

Portfolio Process Assets updates, Portfolio Charter updates, Portfolio Reports updates, Portfolio Management Plan updates, Portfolio Component Reports updates


C.

Portfolio Process Assets updates, Portfolio Management Plan updates


D.

Portfolio Process Assets updates, Portfolio Roadmap updates, Portfolio updates, Portfolio Management Plan updates, Enterprise Environmental Factors updates