PMI Portfolio Management Professional PfMP Question # 139 Topic 14 Discussion

PfMP Exam Topic 14 Question 139 Discussion:
Question #: 139
Topic #: 14

Risk management is an integral part of project, program and portfolio management and is invoked throughout the project, program and portfolio life cycle. Which of the following highlights the difference between portfolio risk and program or project risks?


A.

Portfolio risks focus on strategies, whereas program and project risks focus on implementation


B.

Portfolio Risks may be actively accepted in anticipation of high rewards, whereas, program and project level risks are not


C.

Portfolio risks are the aggregation of subsidiary programs and projects risks


D.

Portfolio risks can not be mitigated to other third parties, whereas program and project risks can