Stakeholders are concerned about the purpose of optimizing a portfolio while already having defined the portfolio with its related components, and are worried that this will cause a lot of time to be wasted. What is your advice to the stakeholders?
A.
This process is required to produce an organized portfolio for ongoing evaluation, selection, and prioritization
B.
This process is required to optimize and balance the portfolio for performance and value delivery
C.
They are right, the process can be skipped when an inventory of work is in place
D.
This process can be skipped because it will be re-done as part of the Optimize Portfolio process