PMI Portfolio Management Professional PfMP Question # 83 Topic 9 Discussion

PfMP Exam Topic 9 Question 83 Discussion:
Question #: 83
Topic #: 9

When developing the charter, you will use multiple inputs and documents of which the portfolio Strategic Plan is one. How is the strategic plan used in this case?


A.

It is not an input to this process


B.

The Portfolio Structure and Portfolio Manager's Authorizations are copied from the Portfolio Strategic Plan as is and incorporated in the Charter


C.

It is updated based on the output of the Develop portfolio charter process


D.

The prioritization model is used as a decision framework to structure the portfolio components