Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMI-200 All Questions
Exam PMI-200 All Questions

View all questions & answers for the PMI-200 exam

PMI ACP PMI-200 Question # 1 Topic 1 Discussion

PMI-200 Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

A project's first iteration contains item A and its second iteration contains item B The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar, a team member suggests beginning the design of item B.

What should the agile practitioner do?


A.

Defer starting the design of item B until the second iteration is being planned


B.

Proceed with the design of item B; since it will hasten the second iteration


C.

Escalate the issue to the customer, and obtain their approval before starting the design of item B


D.

Log the issue in the risk register, and request change control board (CCB) approval


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.