During an agile team retrospective, some junior team members discussed an approach that could improve the overall team performance. How should the agile practitioner handle the recommendation?
A.
Record the suggestion to be considered for future projects.
B.
Invite the team to evaluate the suggestion and measure the effectiveness of the implementation.
C.
Let the product owner consider the proposal and decide whether to adopt the suggested practice.
D.
Let the team's senior members decide whether to adopt the suggested practice.
Chosen Answer: