PMI ACP PMI-200 Question # 91 Topic 10 Discussion

PMI-200 Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.

What is the role of the team?


A.

Estimate and define the work items.


B.

Assess user story quality and independent, negotiable, valuable, estimable, small, and testable (INVEST) criteria.


C.

Add features to the product backlog.


D.

Determine if the demand is or is not feasible.