Project stakeholders are finding it difficult to know the real-time status of who has been assigned to various stories and the status of each work item. Which of the following should the agile project manager do?
A.
Use an information radiator to help increase the transparency of work for key stakeholders.
B.
Send status updates whenever the stakeholders request them.
C.
Hold Scrum meetings more frequently to ensure stakeholders are well informed.
D.
Instruct the team to focus on their own assignments rather than the work of others.
Chosen Answer: