PMI ACP PMI-200 Question # 100 Topic 11 Discussion

PMI-200 Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?


A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.


B.

Ask the team to find a workaround so that they can continue with the current project management plan.


C.

Advise the team to continue working on the sprints as the release plan has been set.


D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.