PMI ACP PMI-200 Question # 106 Topic 11 Discussion

PMI-200 Exam Topic 11 Question 106 Discussion:
Question #: 106
Topic #: 11

A new project has been approved and is critical for an organization. The project sponsor has a limited budget, and the deadline to have all requirements meet the definition of done (DoD) is short.

Which approach should the agile practitioner take to facilitate the project's success?


A.

Set up weekly calls with the key stakeholders to participate in iteration reviews and release decisions.


B.

Analyze the impacts of these constraints on the project followed by a report sent to the sponsor to anticipate any risk of delays.


C.

Set up a meeting with the client to review the scope and timelines to manage expectations.


D.

Encourage the team to build increments and ensure the customer provides early feedback for a minimum viable product.