An agile project manager observes that the Scrum team is falling behind on the completion of a particular sprint. What should the agile project manager do?
A.
Facilitate by providing directions to the team about how they can get back on track.
B.
Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.
C.
Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.
D.
Understand the impediments and facilitate issue resolution to enable the team to succeed.
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit