During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?
A.
The story should be assigned eight story points as per the majority vote
B.
The story should be added to the backlog and reassessed later
C.
The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
D.
The decision for the number of story points should be made by the customer