The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.
What should the team do next?
A.
Ask for a team extension so that an engineer with the needed experience can be added to the team.
B.
Suggest that the product owner perform the initial investigation and present the outcome to the team.C Request thai the product owner include a spike in the next iteration's backlog so they can perform an initial investigation
C.
Propose alternative components with which the team has experience.
Chosen Answer: