PMI ACP PMI-200 Question # 121 Topic 13 Discussion

PMI-200 Exam Topic 13 Question 121 Discussion:
Question #: 121
Topic #: 13

Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date. What should the agile practitioner do?


A.

Deal with the issues in a retrospective if they ever come up again.


B.

Create a task board to track issues when they appear.


C.

Identify and monitor issues through a risk burndown chart.


D.

Create an issue log as an information radiator and monitor.