PMI ACP PMI-200 Question # 122 Topic 13 Discussion

PMI-200 Exam Topic 13 Question 122 Discussion:
Question #: 122
Topic #: 13

A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?


A.

To produce a fast return on investment


B.

To reduce risk as quickly as possible


C.

To gain competitive advantage as soon as possible


D.

To maintain visibility with project stakeholders