An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?
A.
Dismiss the team member
B.
Discuss the situation with the functional manager
C.
Report the functional manager to the project sponsor
D.
Demand that the functional manager respect the project charter