PMI ACP PMI-200 Question # 130 Topic 14 Discussion

PMI-200 Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

A team using Kanban identifies that their cycle time has significant variation After brainstorming the team determines that the root cause is the stones' varying sizes and risks.

What should the team do?


A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories


B.

Create a triage step on the Kanban board to pre-identify risky stones


C.

Set a policy to break down stories larger than a specified complexity then adjust the WIP


D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large