During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories What should the scrum master do?


A.

Ask the lead developer to identify a solution, and then share the details with the team


B.

Ask a technical manager or architect to determine a solution to the problem


C.

Work with the product owner to add a spike to the next sprint to identify a solution


D.

Create a collaborative team environment so that the team can explore a solution together