Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMI-200 All Questions
Exam PMI-200 All Questions

View all questions & answers for the PMI-200 exam

PMI ACP PMI-200 Question # 10 Topic 2 Discussion

PMI-200 Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

Midway through a project the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project

What should the product owner do next?


A.

Obtain approval from the change control board to discontinue the component


B.

Ask the team to continue developing the component


C.

Ask the team to discontinue developing the component


D.

Request the sponsor's formal approval to discontinue the component


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.