An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?
Regularly circulate an updated, detailed version of the project plan
Frequently update the online project management office (PMO) repository site
Invite the stakeholders to daily stand ups
Post a project board in an area where all can view it