PMI ACP PMI-200 Question # 19 Topic 2 Discussion

PMI-200 Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.

How should the agile lead implement an effective and efficient solution?


A.

Review the quality assurance and control processes with the team to ensure that even new team members understand the service level agreement (SLA) made with the customer.


B.

Suggest the team commit to a 2-month trial using Kanban. Focus on delivering value to the customer using pull criteria before advancing work. The team will have planning meetings as needed with no special meetings about the process.


C.

Hire a consultant team to perform a root cause analysis, which will determine the fundamental issues from both perspectives, then meet with the team to determine the best method to get the project back on track.


D.

Work with the team to create a spike story for the next iteration to investigate the issue. Create a plan to get the project back on track and present it at the next status meeting to gain stakeholder acceptance.