PMI ACP PMI-200 Question # 24 Topic 3 Discussion

PMI-200 Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the scrum master do?

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the scrum master do?


A.

Report the issue to the product owner and request help.


B.

Let the new release manager participate in the daily standup.


C.

Invite the new release manager to the sprint demo and ask for help.


D.

Send a status report to the release manager highlighting the issue.