An agile project manager is planning the initial scope, schedule and cost range estimates on a new project. The team will be using Kanban to control work.
What metrics should the team use to measure performance?
A.
Lead time, throughput and due date performance
B.
Work in progress limits Kanban board, and time boxes
C.
Work item types, sprint cadences, and defect classes
Chosen Answer: