PMI ACP PMI-200 Question # 28 Topic 3 Discussion

PMI-200 Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?


A.

Shared vision statement and sprint goal


B.

Release burnup chart


C.

Velocity metrics


D.

Iteration burndown chart