A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.
What should be done to resolve this challenge?
A.
Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.
B.
Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.
C.
Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.
D.
Implement a spike lo enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit