PMI ACP PMI-200 Question # 57 Topic 6 Discussion

PMI-200 Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog. What should the team do first to define the tasks needed to implement the user stories?


A.

Self-organize


B.

Assign tasks to each team member


C.

Meet with the customer


D.

Identify the Scrum Master