PMI ACP PMI-200 Question # 61 Topic 7 Discussion

PMI-200 Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?


A.

Lead time


B.

Team velocity


C.

Burndown rate


D.

Earned value (EV)