PMI ACP PMI-200 Question # 75 Topic 8 Discussion

PMI-200 Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The team expresses frustration during a standup.

What should the Scrum Master do?


A.

Ask the product owner how upper management's comments can be redirected.


B.

Direct the developer team to ignore the phone calls and emails.


C.

Ask the product owner to enter the requests into the product backlog as high priority.


D.

Personally respond to upper management's phone calls and emails.