PMI ACP PMI-200 Question # 87 Topic 9 Discussion

PMI-200 Exam Topic 9 Question 87 Discussion:
Question #: 87
Topic #: 9

An agile team is working on refining project requirements. Due to new dependencies uncovered in every working session, the team is unable to complete the detailed solution requirements. Instead of trying to complete requirements, what should the team do to work collaboratively to identify and prioritize the most important requirements and adapt to changes as needed?


A.

Report this as a blocker and ask senior management to provide the right subject matter experts (SMEs) until all the outstanding issues can be dosed.


B.

Identify the key business stakeholders and invite them to day-long sessions until all the dependencies and outstanding issues can be closed.


C.

Identify the key dependencies that need to be resolved in order of priority level so the user stories can meet the definition of ready (DoR) criteria.


D.

Report this as a blocker and ensure the product owner is able to deprioritize the issues so the user stories can meet the definition of ready (DoR) criteria.