Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMI-PBA All Questions
Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

PMI Professional in Business Analysis PMI-PBA Question # 4 Topic 1 Discussion

PMI-PBA Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?


A.

Develop a change control process.


B.

Obtain approval from the project sponsor.


C.

Document changes as they occur.


D.

Hold firm on scope and reject changes.


Get Premium PMI-PBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.