PMI Professional in Business Analysis PMI-PBA Question # 52 Topic 6 Discussion

PMI-PBA Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?


A.

Multivoting


B.

MoSCoW


C.

Time-boxing


D.

Budget analysis