A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?


A.

Review potential next steps with the project team.


B.

Review the scope of work to determine the prescribed project methodology.


C.

Review the policies and practices that are outlined in the risk management plan.


D.

Review the contract and determine the resources and project funding.