Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMI-RMP All Questions
Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

PMI PMI-RMP Question # 4 Topic 1 Discussion

PMI-RMP Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?


A.

US$18,000


B.

US$72.000


C.

US$30,000


D.

US$48,000


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.