Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMI-RMP All Questions
Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

PMI PMI-RMP Question # 20 Topic 3 Discussion

PMI-RMP Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?


A.

Compare the actual data with the historical data.


B.

Compare the actual data with the subject matter expert (SME) criteria.


C.

Compare the actual data with the risk baseline.


D.

Compare the actual data with the project sponsor's expectation.


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.