Question #: 24
Topic #: 3

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?


A.

Product Manager


B.

Risk Action Owner


C.

Risk Owner


D.

Project Manager