PMI PMI-RMP Question # 40 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?


A.

Continue to implement the risk strategy


B.

Meet with team members to address their concerns.


C.

Reduce the number of risk management activities.


D.

Raise the concerns with the project sponsor,