PMI PMI-RMP Question # 43 Topic 5 Discussion

PMI-RMP Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?


A.

Review assumptions and constraints around risks.


B.

Develop the risk response plans for identified risks.


C.

Determine the likelihood and impact of the risks.


D.

Apply an iterative approach to risk identification.