An organization is embarking on a multi-million-dollar project with numerous identified risks. What should the project risk team do to navigate the risks on this project?


A.

Go for a low-risk threshold of ±5% around a cost objective.


B.

Confirm stakeholders risk thresholds based on risk appetites.


C.

Conduct risk identification to populate the risk register.


D.

Go for a high-risk threshold of ±10% around a cost objective. 