Question #: 54
Topic #: 6

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?


A.

Perform a sensitivity analysis to the higher-level aggregate activities


B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories


C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis


D.

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives