PMI PMI-RMP Question # 63 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 63 Discussion:
Question #: 63
Topic #: 7

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?


A.

Add contingencies to other tasks to mitigate similar risks.


B.

Reassess risks with a new assumptions and constraints analysis.


C.

Review the risk response plan looking for lessons learned.


D.

Log the event in the issue log and update the project management plan.