PMI PMI-RMP Question # 65 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 65 Discussion:
Question #: 65
Topic #: 7

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?


A.

Request a budget relief using the management reserve.


B.

Conduct a risk reassessment and reserve analysis.


C.

Review the consequences of potential changes.


D.

Coach stakeholders on risk identification practices.