Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMI-RMP All Questions
Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

PMI PMI-RMP Question # 66 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 66 Discussion:
Question #: 66
Topic #: 7

The risk manager loaded the risk register, built the risks into the simul-ation software, and ran the Monte Carlo analysis. The P80 and P90 end dates are the same as the deterministic date.

What should be the risk manager's next step?


A.

Check the schedule for constraints


B.

Use the P90 date on the risk report


C.

Decrease the number of iterations


D.

Decrease the risk consequences


Get Premium PMI-RMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.